It's July and you haven't placed your autumn-winter sweater order yet? You still have time, but the window is closing.
The peak season for knitwear factories typically runs from late July through October. If you plan to launch fall-winter products in September-October, now is the critical decision point.
This article works backwards through the timeline, telling you what to do at each stage and how much time to allow.

1. The Latest Timeline: 16–18 Weeks Working Backward
Starting from your desired warehouse arrival date and working back, a typical fall-winter sweater OEM order needs 16–18 weeks. Taking an October launch as the target:
| Stage | Timeframe | Duration | Notes |
|---|---|---|---|
| Inquiry & quotation | Mid-June to early July | 1–2 weeks | Confirm style, yarn, quantity, price |
| Sampling | Early to mid-July | 6–10 working days | Produce sample, revise, approve |
| PP sample approval | Mid to late July | 3–5 days | Final confirmation before bulk production |
| Yarn sourcing | Late July to early August | 5–10 days | Order yarn for bulk production |
| Bulk production | Early to late August | 18–25 days | Scheduled per order volume |
| Finishing + QC | Late August to early September | 3–5 days | Washing, pressing, final inspection |
| Sea freight to port | Early to late September | 15–25 days | China port to destination port |
| Customs clearance & warehouse | Late September | 3–7 days | Customs + warehousing |
| In stock & on shelf | Early October | — | Start selling |
If your target is an October launch, sampling should be confirmed by the end of July at the latest, and bulk production must start by mid-August.
2. What If You've Missed the Window?
Scenario 1: It's late July and you haven't sampled yet
You still have a chance, but you need to take the "fast track":
- Choose stock yarns (black, white, navy, grey — basic colors that factories keep in stock, eliminating the ordering lead time)
- Choose standard silhouettes (select from the factory's existing sample library and modify, saving pattern development time)
- Use air freight to make up time (sea freight 15–25 days → air freight 5–8 days, shipping costs 3–5 times higher but won't miss the season)
- Reduce the first order quantity to shorten production time (300 pieces vs. 1,000 pieces — about 7–10 days difference in production time)
Scenario 2: It's September — can I still do fall-winter styles?
Yes, but you need to pick the right categories:
- Choose fine-gauge lightweight styles (12G and above, weight ≤ 300g/piece, high production efficiency)
- Do deep reorders rather than new style development (skip sampling, add colors and quantities to existing patterns)
- Accept partial air freight (basic colors by sea, trendy colors by air to sell first)
Scenario 3: You remember in November
It's basically too late for fall-winter at this point. Instead, pivot to: spring styles for next year. Many factories enter their spring development cycle in November. Sampling spring styles now puts you right on schedule for a February-March launch.

3. 5 Things Brands Must Confirm in Advance
Before confirming bulk production scheduling with the factory, these 5 items must be clarified:
- Is the yarn in stock? Non-stock yarns (e.g., special dye colors, imported yarns) need an additional 7–15 day ordering lead time
- Will multiple colors be produced together or separately? Producing multiple colors in a single batch saves 10–15 days compared to separate runs
- Sea freight or air freight? Air freight can secure an October launch but costs 3–5 times more; sea freight is cheaper but adds 15–20 days
- Are you making complex styles? Patterns like jacquard, intarsia, and fully-fashioned designs add 5–10 days compared to solid-color styles
- Does this overlap with Chinese New Year? Factories shut down for 15–20 days around the holiday; fall-winter orders placed in January may not ship until March
4. How to Use Factory Capacity Cycles to Your Advantage
| Period | Factory Status | Impact on Brands |
|---|---|---|
| March–May | Low season | Sample during low season, produce in peak season (recommended) |
| June–July | Transitioning to busy | Fast sampling, ample bulk scheduling |
| August–September | Peak season | Tight scheduling, rush fees may apply |
| October–December | Peak season peak | Longest lead times — avoid placing new orders here |
| January–February | Chinese New Year shutdown | Cannot accept orders; pre-holiday orders ship after |
Best strategy: Sample and confirm during the low season (March–May), place bulk orders in June–July, ship by sea in August–September, and arrive at warehouse in October. If you've already missed this, at least make sure sampling is done in the low season so you can go straight into bulk production when peak season hits.

What's the latest I can order fall-winter sweaters?
If you want an October launch, sampling should be confirmed by the end of July, with bulk production starting by mid-August. If using air freight, you can push sampling to early August and bulk orders to late August, with air freight arriving by end of September. Based on our factory's experience, late July still offers ample time; mid-August is tight; and by September you are essentially on an air freight route.
What should I know about ordering before Chinese New Year?
Before Chinese New Year (typically starting mid-to-late January), factories gradually shut down for the holiday and don't fully resume until after the Lantern Festival — about 15–20 days of shutdown. If your order spans the CNY period, make sure you have the factory's holiday schedule and either complete bulk production before the shutdown or accept post-holiday delivery. Recommendation: place all your fall-winter orders before December, then start on spring-summer after CNY.
Can I order yarn before sampling is confirmed?
Not recommended. Once ordered, yarn cannot be returned — each type has a minimum order quantity (typically 20-50kg per color). If you order yarn before sampling is confirmed and the style or color needs changes, the yarn is wasted. The correct sequence: sampling confirmed → PP sample approved → order yarn → bulk production. Don't skip steps.
It's still early July — the autumn-winter sweater procurement window remains wide open. As long as you confirm styles, yarns, and quantities before the end of this month, an October launch is entirely achievable.
To discuss specific lead times, contact us with your planned launch date and estimated quantities, and we'll provide a precise timeline based on actual scheduling. You can also learn about our production process and customization service scope.